Chadstone Shopping Centre

CHADSTONE SHOPPING CENTRE STAGE 30

CHADSTONE VIC

As at April 2008, the structure is well into construction. The Office Building is constructed up to Level 2, the Bulky Goods building is 90% complete and the Financial Precinct and Supermarket buildings are in the final stage of steelwork erection. Road and carpark civil works are scheduled for completion by the end of April 2008.

Bendigo Bank Building

BENDIGO BANK BUILDING

BENDIGO VIC

Construction of the main office building is now complete with project works now commencing in the existing building. The glazed main entry structure is currently being fabricated and is scheduled to be delivered to site at the end of April, 2008.

Northland Shopping Center

(last updated April 2008)

NORTHLAND SHOPPING CENTRE STAGE 20

PRESTON VIC

Zone 1 Early Works commenced in September 2007 and are now complete with the relocation of Toys R Us and The Reject Shop and redevelopment of Bus Bays. The tender and contract award process for the main project works is now complete and piling works have begun on site. Zones 2 to 8 form the initial stage of the main works contract which consists of mall realignments, Cole relocation, additional mini major stores and new carparks. The largest stage, Zone 9, is scheduled to commence in October, 2008, with construction through 2009. Zone 9 includes new malls, basement carparking, new Target Store and numerous new tenancies.